Every business that grows fast eventually books more than it can deliver. A supplier misses, a line goes down, a component goes on allocation upstream, or sales simply sells the year in a quarter. The result is the same: committed demand exceeds available supply, and somebody is not getting what they ordered.
Most teams handle this badly in an identical way. They do not decide. They let the order queue decide — first in, first out — then tell customers when the ship date is already missed. FIFO feels fair, which is why it is so popular, and it is the single most expensive rule you can run, because it hands your scarce units to whoever happened to order earliest rather than to whoever matters most.
Allocation is a decision. This is how to make it deliberately, in about a week, and how to communicate it without torching the relationships you are trying to protect.
Step 1: Establish the real number, once
Before you can ration anything you need one honest figure: units available to promise, by period, for the next two quarters. Not capacity. Not forecast. Available to promise — what you can actually ship after subtracting work in progress, safety stock you will not touch, and the units already spoken for by contracts with delivery penalties.
Build it as a simple table by month:
- Gross supply — what you expect to receive or produce.
- Less: contractually locked — orders with penalty clauses or take-or-pay terms.
- Less: buffer — an explicit number, typically 5–10%, for warranty replacement and the mistake you have not found yet.
- Equals: allocatable units.
Two rules about this number. It gets one owner, not a committee. And it gets refreshed on a fixed day each week, because the entire method below collapses the moment two departments are working from different totals. If ops says 4,200 and sales is quoting against 5,000, you have not built an allocation plan, you have built an argument.
Step 2: Score customers on value, not volume
The instinct is to protect the biggest accounts. Sometimes that is right. Often it is exactly wrong — the biggest account is frequently the lowest-margin one, the one with the most aggressive procurement team, and the one that will switch on price the moment supply loosens anyway.
Score every account that has demand in the window on four dimensions, 1 to 5:
- Gross margin per unit. Not revenue. If you have one unit to give, give it where it earns most.
- Switching cost for them. How hard is it for this customer to go elsewhere? A customer who can replace you in a fortnight is a customer you can lose in a fortnight.
- Strategic weight. Reference value, category access, a logo that closes other deals, a design win that locks you into a platform for years.
- Behaviour under stress. Who paid on time last crunch? Who escalated to your CEO over a two-day slip? This is legitimate input and everyone pretends it is not.
Sum the four. Sort descending. You now have a defensible order, and — more importantly — you have a written rationale you can repeat to an angry VP without improvising.
Step 3: Pick a rule, then apply it mechanically
Three rules cover almost every situation. Choose one per product line and stick to it for the whole allocation period.
Pro-rata haircut. Everyone gets the same percentage of their order. Simple, easy to explain, nobody is singled out. Use it when your customer base is homogeneous and you cannot afford the political cost of visible ranking. The weakness: it disappoints everyone slightly, which in practice means your best account and your worst account are equally annoyed with you.
Tiered fill. Top tier gets 100%, middle gets 70%, bottom gets what is left. Use it when the score spread in Step 2 is wide — when a handful of accounts genuinely carry the business. The weakness: it is discoverable. Customers talk, and the bottom tier will eventually learn it exists.
Commitment-weighted. Fill rate rises with what the customer is willing to commit: longer term, prepayment, wider delivery window, or a forecast they will be held to. Use it when the shortage will last more than two quarters, because it converts a crisis into contracted backlog. The weakness: it takes longer to negotiate, so it does not work if you need to allocate by Friday.
Whichever you choose, write the rule down in one sentence and make sure every person who talks to customers can recite it. A rule that lives only in the head of the VP of Ops is a rule that will be broken by a salesperson on a Tuesday.
Our take: The exception is what kills you, not the shortage. Every allocation plan survives contact with reality until one senior person overrides it for one important customer. That single override tells the organisation the rule is negotiable, and within a fortnight allocation is decided by whoever escalates loudest. If you must allow exceptions, cap them in advance — a named pool of, say, 5% of allocatable units, controlled by one executive, drawn down visibly. When the pool is empty, it is empty.
Step 4: Tell them early, in a specific order
Customers forgive a short order. They do not forgive finding out on the dock. The cost of bad news roughly doubles for every week you sit on it, because every week you stay quiet is a week they spend planning around inventory that is not coming.
Sequence the calls deliberately: worst-affected first, biggest accounts first within that group, and everyone inside 72 hours so nobody hears it secondhand. Put it in writing the same day.
A script that works, for a customer taking a 40% cut:
“I need to give you a number you are not going to like, and I want you to have it now rather than in three weeks. For Q4 we can confirm 600 units against your order of 1,000. That is firm — I am not going to revise it down again. Here is what drove it: our own supply came in short and we have allocated on margin and contract term rather than order date, which means some customers are seeing deeper cuts than you. Here is what I can do: I can hold the 600 to your original dates, I can give you first call on anything that frees up, and if you can take delivery in the first week of January instead of December I can add 250 more. What would you like me to protect?”
Four things are doing work in that script. A specific number instead of a range. A commitment not to cut again. A reason that is a method rather than an apology. And a question at the end that hands them a decision, because a customer with a choice is a customer who is participating rather than absorbing.
What not to say: “unprecedented demand” (they hear: you sold our units to someone else), “we’re doing everything we can” (says nothing), or any date you are not certain of. One missed recovery date costs more credibility than the original shortfall.
Step 5: Decide what the shortage is worth
A shortage is a pricing signal, and pretending otherwise leaves money on the table while failing to reduce demand. But raising price during a shortage is how you get remembered as an opportunist, so the move is to price the option, not the unit.
Things you can charge for without gouging:
- Priority position — a premium for guaranteed fill rate, bought in advance, available to anyone.
- Expedite fees that reflect what expediting actually costs you, itemised.
- Term commitment discounts — functionally a price rise for anyone who stays spot, framed as a reward for anyone who commits.
And the one to resist: an across-the-board increase announced in the same message as the shortfall. Doing both at once converts a supply problem into a trust problem. Separate them by a quarter.
Worked example
A components maker has 4,200 allocatable units against 6,800 of demand — a 62% fill rate. Scoring puts three accounts at 16–18 points (high margin, hard to switch, strategic), nine at 9–14, and eleven below 9.
Under FIFO, the three top accounts would have received about 40% of their orders, because they order late and in large blocks. Under tiered fill, they get 100% (1,900 units), the middle nine get 70% (1,750), and the bottom eleven split the remaining 550 — roughly a 20% fill, with three of them told plainly they will get nothing this quarter and offered help finding an alternate source.
That last part is not charity. A small customer you helped source elsewhere during a shortage comes back. A small customer who discovered on the dock that they were last in line does not.
The four failure modes
- The silent haircut. Shipping short without telling anyone and hoping the partial delivery speaks for itself. It does — it says you were not willing to have the conversation.
- The rolling promise. Revising the date weekly. Each revision is a fresh disappointment; one honest date, held, costs less than four optimistic ones.
- The escalation market. Exceptions granted to whoever complains hardest. Within a month you have taught every buyer that the route to supply is your CEO’s inbox.
- Allocating on revenue. The most common and the most expensive. Revenue is not margin, and volume is not loyalty.
The one-week version
- Monday: lock the allocatable number. One owner.
- Tuesday: score every account on the four dimensions. Two hours, not two weeks.
- Wednesday: choose the rule, set the exception pool and its single owner, write the one-sentence rationale.
- Thursday: brief everyone customer-facing. Same script, same numbers.
- Friday: make the calls, worst-affected first, written confirmation the same day.
Shortages end. What survives them is the record of how you behaved while supply was the thing you controlled and your customers did not. Allocate on purpose, say it early, and hold the number you gave.