Cost-share programmes are everywhere now: compute subsidies, energy retrofits, export grants, training credits, R&D matching. They all advertise the same way — a big percentage and a big fund size — and the percentage is never what you receive.
This is the procedure for working out what one actually pays you, and whether the application is worth the hours, before you commit a quarter to it. It takes about 90 minutes with the programme guidelines open. Every step produces a number you can defend to a CFO.
Step 1: Convert the percentage into your gap
The advertised rate tells you the programme's share. You need yours, in dollars, in the period you have to pay it.
Write three lines:
- Project cost — the full thing, as you would actually buy it.
- Programme share — cost × the rate.
- Your gap — cost − programme share.
Worked example throughout this playbook: a $1,000,000 compute project under a programme advertising “up to 80% of eligible costs”, with a lower 50% tier for some suppliers.
At 80%, your gap is $200,000. At 50%, it is $500,000. The spread between the two tiers — $300,000 — is larger than the gap at the better tier. Write that spread down. It is usually the single biggest number in the whole analysis, and it is decided by a qualification rule, not by your project.
Step 2: Strike out the ineligible costs
“Eligible costs” is the load-bearing phrase and it is always narrower than your project. Go through the guidelines and mark every cost category as in, out, or unstated. Things that are routinely out:
- Internal salaries, or salaries above a stated cap
- Anything bought before the approval date — retroactive spend is the most common disqualifier
- Hardware you keep, as opposed to capacity you rent
- Taxes, duties, shipping, currency conversion
- Overhead, rent, admin, and anything described as “general operating”
- Costs already claimed under another programme (stacking limits)
Now redo Step 1 on the eligible subset only. In the worked example, suppose $700,000 of the $1,000,000 is eligible and $300,000 is not. At the 80% rate the programme pays $560,000 — and your real gap is $440,000, not $200,000.
That is the whole trick. An “80% covered” programme on a 70%-eligible project is a 56% programme. Compute your effective rate and use only that number from here on: programme share ÷ total project cost.
Step 3: Find the reimbursement lag
Most cost-share money is reimbursement, not prepayment. You spend, you claim, you wait. Three questions decide whether you can survive the mechanics:
- Is it paid in advance, in milestones, or on completion?
- What is the claim cycle — monthly, quarterly, annually — and the stated processing time after a claim?
- What proof does a claim need? Invoices, proof of payment, timesheets, an audit? Each one adds weeks.
Build a crude cash curve: your spend by month, the reimbursement by month, and the running difference. The worst point on that curve is the working capital the programme requires you to have. In the worked example, quarterly claims with a 60-day processing window on a 12-month project means fronting roughly a quarter's eligible spend — about $175,000 — continuously.
If that number exceeds your available cash, the programme is not affordable at any percentage. Stop here and say so.
Step 4: Price the application
Estimate four things and put a dollar figure on each:
- Hours to apply. Count everyone, including the technical staff who have to write the methodology. Multiply by a loaded hourly rate.
- Hours to comply. Reporting, claims, record-keeping, and any audit, across the life of the project.
- Consultant or grant-writer fees, if you use one. Success-fee arrangements are a percentage off your net.
- Opportunity cost. What the same hours would have produced.
Then divide: application-and-compliance cost ÷ expected programme share. If a $560,000 award costs you $60,000 of effort, that is an 11% transaction cost, and your effective rate drops from 56% to about 50%. Which, in the worked example, is the lower tier. The subsidy premium can be entirely consumed by the process of claiming it.
Step 5: Test the tiebreaker condition
Nearly every two-tier programme has one rule that decides which tier you land in: supplier nationality, project location, business size, sector, headcount, a certification. Find it and ask one question: can I verify today that I qualify?
Three possible answers, three different decisions:
- Published and checkable — a named list, a defined test. Model the tier you qualify for.
- Defined but not yet published — the criterion exists, the qualifying list does not. Model the lower tier and treat the difference as upside. Never build a budget on an unpublished list.
- Undefined — assessed case by case with no criteria given. Model the lower tier and add schedule risk, because discretion means delay.
Script for the programme officer, by email, kept to five lines:
“We are preparing an application for the [date] intake. Three questions so we can budget accurately: (1) Is there a published list of suppliers that qualify for the higher cost-share rate, or a test we can apply ourselves? (2) Are [specific cost category] and [specific cost category] eligible? (3) What is the typical interval between an approved claim and payment? Happy to take approximate answers.”
Send it before you write anything. The reply, or the absence of one, is itself a data point about how the programme is run.
Step 6: The go/no-go rule
Four tests. All four have to pass.
- Effective rate ≥ 35% after ineligible costs and transaction costs. Below that, the money is rarely worth the constraint it attaches.
- Peak cash gap is affordable without new borrowing.
- You would do most of the project anyway. This is the one people fail. A subsidy that causes a project is a subsidy that is choosing your strategy.
- The deadline is survivable without pulling people off revenue work in your busiest fortnight.
If three pass and one fails, do not negotiate with yourself. Note which one failed, and whether the next intake would fix it.
The one-page worksheet
Keep this as a template and fill it once per programme:
- Programme name, intake deadline, decision date
- Advertised rate / tier conditions / which tier you can verify
- Total project cost / eligible subset / effective rate
- Payment mechanism / claim cycle / peak cash gap
- Application hours / compliance hours / fees / transaction cost %
- Repayable, conditionally repayable, or non-repayable
- Stacking limit with other programmes
- Clawback triggers
- Go / no-go, and which test decided it
Six ways this goes wrong
- Quoting the advertised rate internally. Someone repeats “80% covered” in a board deck, the budget gets built on a 20% gap, and the real 44% gap arrives in month three. Only ever circulate the effective rate.
- Assuming a grant. Many programmes decide repayability during assessment. “Up to 80% covered” can resolve to a repayable advance. Ask before you model it as free.
- Spending before approval. Costs incurred before the eligibility date are usually disqualified in full, and the project you already started is the one you cannot claim.
- Scope inflation to hit the ceiling. A programme with a $5 million cost cap tempts a $2 million project to become a $5 million one. You now owe your gap on the inflated number.
- Ignoring the end date. A hard programme deadline shortens every project approved near it. Check that your timeline fits inside the window, not just inside your plan.
- Missing the clawback. Headcount commitments, location commitments, and milestone conditions can require repayment years later. Read that clause before the rate.
The 20-minute version
If you only have time for one pass: find the eligible-cost definition, compute the effective rate, find the payment mechanism, and find the tiebreaker rule. Those four facts kill or confirm roughly nine out of ten of these programmes, and three of them are usually in the guidelines' footnotes rather than the press release.
The press release gives you the fund size and the percentage. Neither is a number you can spend.