Somewhere in your supplier base, someone is about to tell you a delay is not their fault. A permit, a port, a plant fire, a regulator, a war, a chip allocation. They may be right. They may also be using the one clause in the contract that converts their operational failure into your problem, and hoping you do not read it closely for three weeks.
Force majeure is the most misunderstood provision in commercial contracting. Most people think it means “act of God, nobody pays.” It does not. It is a narrow, technical, heavily conditioned allocation of schedule and cost risk, and the side that handles the first 72 hours well usually keeps the leverage for the rest of the dispute.
This is the playbook for both directions: receiving a notice, and sending one.
The core idea: force majeure is not a verdict, it is a claim. A notice does not suspend anything by itself. It opens a process in which the claiming party carries the burden of proof on four separate elements, and each one is contestable. Treat the notice as the start of a negotiation you are already scoring, not as news you have received.
Part 1 — The four-element test
Almost every force majeure clause, whatever the drafting, requires the claiming party to establish four things. Write these across the top of a page the day a notice arrives.
- Enumerated event. Did the thing that happened appear in the clause’s list, or in its catch-all? Lists are construed narrowly. “Governmental action” usually covers a permit denial. “Acts of God” usually does not cover a supplier’s subcontractor going bankrupt. If the event is not on the list and the catch-all is a closed “other similar events” formulation, the claim can fail on element one alone.
- Causation. Did that event actually cause the non-performance, or did it coincide with it? This is where most weak claims die. A supplier who was already four weeks late when the hurricane hit gets relief for the hurricane, not for the four weeks.
- Unforeseeability and beyond reasonable control. Could they have anticipated it at signing? A regulatory deadline that was public when the contract was signed is a planning failure, not a force majeure. Rising prices are almost never force majeure; economic hardship is specifically excluded in most modern drafting.
- Mitigation. Did they take reasonable steps to work around it? Nearly every clause imposes a continuing duty to mitigate, and nearly every claiming party forgets to document that they tried.
If you can defeat any one element, the claim fails. Score all four before you reply to anything.
Part 2 — The first 72 hours after receiving a notice
Hour 0–4: Do not respond substantively. Acknowledge receipt in writing, note the date and time, and say nothing about whether you accept it. The single most common unforced error is a well-meaning operations lead replying “understood, keep us posted,” which counsel on the other side will later characterise as acceptance.
Use this:
“We acknowledge receipt of your notice dated [date] at [time]. We are reviewing it against the requirements of Section [X] and reserve all rights and remedies under the Agreement. Please provide, within [5] business days: (a) the specific subsection relied upon; (b) a detailed statement of causation; (c) your mitigation plan; and (d) your good-faith estimate of duration. Nothing in this acknowledgement constitutes acceptance of the claim.”
Hour 4–24: Pull the clause and the notice provisions. Check three procedural requirements that void claims more often than substantive ones: the notice deadline (often 5 to 15 days from the event, not from the impact), the required method of delivery, and the required content. A notice delivered by email when the contract requires courier, or sent 20 days after a permit denial under a 10-day clause, is frequently fatal to the claim regardless of merit.
Hour 24–48: Build the timeline. One page, dated rows, sourced. When was the contract signed. When did the event become publicly foreseeable. When were they already behind. When did they notify. The gap between “event became foreseeable” and “contract signed” is your unforeseeability argument. The gap between “already behind” and “event” is your causation argument.
Hour 48–72: Quantify your exposure. Three numbers: the cost of the delay to you per week; the cost of covering from an alternative source; and the value of the relationship over the remaining term. You cannot negotiate without all three, and the third one is the one people skip and then regret.
Part 3 — The response letter
After the timeline, you have three positions available. Pick deliberately.
- Reject. Use when an element clearly fails or the procedure was botched. State which element and why, in one paragraph each. Demand performance by the original date. Reserve rights.
- Accept partially. The most common correct answer. Accept relief for a defined window tied to the event, explicitly reject relief for any pre-existing delay, and require weekly mitigation reporting. This is where you preserve the relationship and the clock at the same time.
- Convert. Accept the delay and trade it for something: a price concession, extended term, priority allocation when supply returns, a most-favoured-customer clause, a termination right if the event runs past a defined outside date. A counterparty who needs relief is a counterparty with a reason to give you something.
Whichever you choose, always insert the outside date: “If the Force Majeure Event continues beyond [90] days, either party may terminate the affected Statement of Work without liability.” If the original contract lacks one, this is the moment to get it.
Part 4 — Sending a notice
If you are the one invoking it, the discipline is inverted but the elements are the same.
- Send early, even if the impact is uncertain. The deadline usually runs from the event, not from the harm. A protective notice sent on day three costs nothing; a late notice can void an otherwise valid claim.
- Cite the subsection. Name the exact clause and the exact enumerated event. Vague notices invite the reply letter you do not want.
- Prove causation in the notice itself. Two or three sentences with dates: the event occurred on X, it prevents Y specifically because of Z. Do not make them ask.
- Lead with mitigation. Describe what you have already done — alternative sourcing explored, expedited freight priced, resequenced work. This is the element that most claims lose on and the easiest one to win on paper.
- Give a duration estimate and update it. An unbounded notice reads as an excuse. A bounded one with weekly updates reads as project management.
- Keep performing everything you still can. Partial performance during a force majeure period is powerful evidence of good faith and is often contractually required anyway.
Part 5 — The six failure modes
- Replying casually. An operations email is a contractual communication. Route the first substantive response through one named person.
- Missing the procedural defect. Check the deadline and delivery method before you argue the merits. It is the cheapest win available and it expires once you engage substantively.
- Accepting a bundled claim. Suppliers routinely fold pre-existing slippage into a force majeure window. Separate the clock into “before event” and “after event” and only grant the second.
- No outside date. An open-ended suspension is a contract you cannot exit and cannot enforce. Always bound it.
- Treating price as force majeure. Cost increases are not force majeure in most drafting. If you need relief for economic hardship, that is a different clause and a different conversation — do not contaminate a valid schedule claim with an invalid price one.
- Forgetting the insurance and the downstream. Notify your insurer within policy deadlines, and check whether your own customer contracts have back-to-back clauses you now need to invoke. A force majeure that stops at you is a force majeure you are funding.
Part 6 — The pre-mortem: fix this at signing
Everything above is easier if you did four things when the contract was drafted.
- Make the list open or closed on purpose. As buyer, push for a closed list with a narrow catch-all. As supplier, push for an open one. Know which side of that you are on before redlining.
- Exclude the predictable. Name the things that should never qualify: labour disputes at the supplier’s own facilities, subcontractor failure, cost increases, and any regulatory process that was already pending at signature.
- Put in the outside date and the termination right. 60 or 90 days is standard. Without it, the clause is a hostage-taking device.
- Add a mitigation reporting obligation. Weekly written updates during any claimed event. This single line converts a dispute about what happened into a dispute about a documented record, which is a much better dispute to have.
The end state: a force majeure notice should take you four days to answer, not four weeks, and the answer should be a partial acceptance with an outside date and a mitigation reporting requirement. That is not legal sophistication; it is a checklist. The parties who lose these are not outlawyered — they are out-organised in the first 72 hours, and they spend the next six months arguing from a position they gave away in an email.
One last thing. Force majeure disputes are disproportionately relationship-ending, and they usually do not need to be. The counterparty is generally not lying; they are usually overstating a real problem because they are frightened of the liability. The playbook above is designed to establish exactly how much of their problem is genuinely yours — and then to give them that much, on the record, in exchange for something, with a date on it. That is a deal both sides can live with. Everything else is litigation.
This is a general commercial-practice guide, not legal advice. Force majeure outcomes turn on the specific wording of your contract and the governing law — involve counsel before relying on or contesting a notice.