Riot Platforms has signed the largest lease in its history: 15 years, 910 megawatts of critical IT capacity, the entire Corsicana campus in Texas, worth about $28 billion over the initial term. The tenant is described in the company's own announcement as a leading frontier AI lab. It is not named.
With Corsicana added, Riot's contracted revenue reaches roughly $38 billion. Nearly all of it now sits with that one unnamed counterparty, which also leases part of the company's Rockdale site. A bitcoin miner has turned itself into a landlord with a single tenant and a two-decade horizon.
Our take: Concentration is the number here, not the $28 billion. Riot has swapped a volatile revenue line it controlled — mining — for a stable one it does not, dependent on one customer's willingness to keep paying for capacity through fifteen years of model cycles. That is a better business and a worse risk profile at the same time. The market's job is to price a counterparty it cannot see, and it has no name to put against the exposure.
What Riot is actually selling
This is not a data-centre operating contract. By TIKR's reading of the structure, Riot supplies the land, the power and the pads; the tenant brings its own computers and covers nearly all operating costs. That is roughly half of what a conventional data centre business does — and it is the half with the 99% net operating income margin TIKR calculates against about $1.8 billion of annual rent. Riot's own Rockdale build cost it $11–12 million per megawatt, which is the capital this structure lets it avoid.
Chief executive Jason Les said “the structure of this new lease matters as much as the scale.” On the Q2 call, when Corsicana was still a letter of intent, he had been equally precise in the other direction: “an LOI is not a signed lease.” It is now signed.
The market split the sector in half
Riot rose about 13% on 4 November on the lease and third-quarter results. The same session, Cipher Mining fell by double digits — reported between 13% and 17% — and MARA dropped about 5%. Mining revenue tells you why the pivot is happening: Riot's fell to $116.0 million in the quarter from $160.8 million a year earlier, and the company has sold 20,264 bitcoin this year to fund construction.
What to watch
- Whether the tenant is ever identified. A fifteen-year, $28 billion obligation disclosed without a counterparty name is a disclosure choice shareholders can ask about.
- Texas permitting. The incoming governor campaigned on suspending new data-centre approvals. Corsicana is in Texas.
- Phase timing. Rockdale's first 96 megawatts are targeted for December 2027 and the full 191 for June 2028. Corsicana has no public schedule.
- The 2029 revenue figure. Riot's signed leases are expected to deliver about $2.3 billion in 2029 — the first year the model is testable.