Business

Georgia Power says the buildout saves you $102 a year. Thirty families are paying with their houses.

The utility’s approved 10-year plan runs more than 1,000 miles of new transmission across 330-plus parcels of land and levels nearly 30 homes along a 35-mile stretch southwest of Atlanta. The state’s own December agreement says roughly 80% of the almost 10,000 megawatts being built is expected to power data centers. Georgia Power says it is “not in the data center business.”

N Noah · The Sharp Brief · July 26, 2026 · 4 min read
Survey marking flags in the front yard of a rural house, with high-voltage transmission towers crossing the field behind it

Nine hours ago we ran the study saying data centers made electricity cheaper for a decade. Here is the same trade, priced in a different currency.

Georgia Power is executing a 10-year plan the Georgia Public Service Commission approved last year: more than 1,000 miles of new transmission line, routed across upward of 330 parcels of land, plus roughly 10 gigawatts of new generating capacity over five years. One piece of it — the Ashley Park–Wansley Transmission Project — runs 35 miles through Fayette, Heard, Fulton and Coweta counties. Building it means leveling nearly 30 houses.

“My childhood home is being taken by Georgia Power,” one affected homeowner, Ansley Brown, said in an Instagram video quoted by Fortune on Sunday. “They are going to bulldoze this entire property to the ground.” Georgia Power told the magazine it has since reached an agreement with Brown’s mother and considers that matter resolved. Land and easement negotiations along the route are “close” to complete. Construction could start as early as next year.

The two numbers that don’t sit together

Georgia Power’s case is a rate case, and it is not a weak one. The utility projects the five projects will deliver about $102 in annual savings per residential customer, beginning in 2029, funded by charging large-load customers more and pushing the difference down onto households. That is the same fixed-cost-divided-by-more-kilowatt-hours arithmetic the EPRI paper described this morning — only here it is written into tariff design rather than inferred from a decade of data.

The other number is the one the utility keeps at arm’s length. A December 2025 agreement between Georgia Power and the PSC certified a nearly 10,000-megawatt generation plan “approximately 80 percent of which is expected to power data centers.” CBS separately estimated 70–80% of the Wansley line’s power will serve AI data centers. Asked about it, a Georgia Power spokesperson said the company is “not in the data center business” and could not confirm the estimate.

On compensation, the utility says it opens at 125% of appraised value and negotiates up from there, and that eminent domain is a last resort used in under 1% of its land transactions — five times in the past year, none of them residential. Homeowners on the route tell reporters the opening offers ran well below what they think the property is worth. Attorneys who work these cases point out the quieter risk: a permanent easement is a contract that stays attached to the deed after you sell, and can bar you from building under the lines while reserving the utility’s right to add more infrastructure later.

Our take: The $102 is real. So are the houses. What makes this a business story instead of a zoning fight is the shape of the ledger: the benefit is diffuse, per-customer and starts in 2029; the cost is concentrated, immediate, and lands on about 30 addresses. Utilities have socialized infrastructure costs for a century — that is the regulated-monopoly bargain. What’s new is that the identifiable beneficiary is private, enormously profitable, and unnamed in the filings. That is precisely the condition under which “public use” stops being a formality and starts being a lawsuit. Georgia Power’s cleanest defense is also its weakest: it isn’t in the data center business, it just built 10 gigawatts the state says is 80% for data centers.

What to watch

Georgia has more than 200 operational data centers, roughly 170 of them around Atlanta. The state built the on-ramp with tax policy and is now building the grid to match. The bill arrives in installments — some on the monthly statement, some at the front door.

Advertisement

Get the day, decoded — at 7 PM ET

The Sharp Brief: AI, money, business & performance in five sharp minutes. Free.

Free bonus: subscribe today and The 2026 Side-Hustle Playbook (PDF) lands with your welcome email.

Recommended by 5+ newsletters across AI, markets & business.